The process for developing a Wind Farm consists of various stages to ensure that the proposed site is suitable to accommodate wind turbines and that potential impacts on the environment are fully understood and can be either avoided or mitigated. An essential aspect of this process is engaging with members of the local community and statutory consultees.

 

August – October 2009

 

Preliminary surveys

 

October 2009

 

Environmental scoping

 

October 2009 – June 2010

 

Detailed environmental survey work
Feasibility and initial scheme design

 

July 2010

 

Detailed environmental survey work
Stakeholder engagement

 

August 2010

 

Public consultation event
Review and update proposals

 

September – October 2010

 

Complete environmental studies
Public exhibition of updated proposals and environmental studies

 

Autumn 2010

 

Finalise proposals and complete Environmental Statement
Submit planning application

 

Early 2011

 

Application determined

 

2011 – 2012

 

Discharge planning conditions
Prepare for tendering of contracts

 

2012 – 2013

 

Tender contracts
Financial close

 

2013–2014

 

Commence construction

 

2015

 

Wind Farm operational