Project timeline
|
The process for developing a Wind Farm consists of various stages to ensure that the proposed site is suitable to accommodate wind turbines and that potential impacts on the environment are fully understood and can be either avoided or mitigated. An essential aspect of this process is engaging with members of the local community and statutory consultees.
| |
August – October 2009
|
| |
Preliminary surveys
|
| |
October 2009
|
| |
Environmental scoping
|
| |
October 2009 – June 2010
|
| |
Detailed environmental survey work
Feasibility and initial scheme design
|
| |
July 2010
|
| |
Detailed environmental survey work
Stakeholder engagement
|
| |
August 2010
|
| |
Public consultation event
Review and update proposals
|
| |
September – October 2010
|
| |
Complete environmental studies
Public exhibition of updated proposals and environmental studies
|
| |
Autumn 2010
|
| |
Finalise proposals and complete Environmental Statement
Submit planning application
|
| |
Early 2011
|
| |
Application determined
|
| |
2011 – 2012
|
| |
Discharge planning conditions
Prepare for tendering of contracts
|
| |
2012 – 2013
|
| |
Tender contracts
Financial close
|
| |
2013–2014
|
| |
Commence construction
|
| |
2015
|
| |
Wind Farm operational
|
|
|