Project timeline

Following the completion of the public consultation, and once all feedback has been considered from the completed questionnaires, we will finalise our planning application and accompanying Environmental Statement. We intend to submit the wind farm application to Northumberland County Council later this year.

Once the planning application is submitted, the Council will commence their own consultation, during which time the public will be invited to formally give their thoughts on the Blue Sky Forest Wind Farm proposals.

 

January - April 2011

 

Feasibility, initial scheme design and environmental scoping

 

March 2011

 

Blue Sky Forest public consultation

 

April - October 2011

 

Detailed environmental assessments

 

October 2011

 

Blue Sky Forest Wind Farm public consultation

 

November 2011

 

Refine proposals and finalise application

 

Winter 2011/12

 

Submit wind farm application and Northumberland County Council consult the public on the proposals

 

Spring 2012

 

Application determined by Northumberland County Council

 

2013 - 2014

 

Construction and commence operation